Q3 2025
Permit approval and site work
Permit approval was received, site clearing is complete, and grading has begun.
Lot Delivery
Baltimore Hill is a 182-lot Huntsville, Alabama lot delivery project acquired for $2.56M.
Market
Huntsville, Alabama
Status
CURRENT
Related fund
Real Estate Fund
Latest update
Q3 2025
Project role
Lots · current
182
Acquisition · current
$2.56M
Timeline
Next
Complete grading and begin utilities.
Q3 2025
Permit approval received, site clearing complete, grading begun.
Q2 2025
Submitted permit and began horizontal development.
Update archive
Q3 2025
Permit approval was received, site clearing is complete, and grading has begun.